Project Name |
On-Line Date |
Capacity (KW) |
Annual Output (KWH) |
| Pioneer Upper, MA |
3/1982 |
1,200 |
4,500,000 |
| Pittsfield, NH |
9/1982 |
400 |
3,000,000 |
| Milo, ME |
12/1982 |
660 |
3,500,000 |
| Pioneer Lower, MA |
12/1982 |
300 |
1,200,000 |
| Hopkinton, NH |
3/1983 |
760 |
4,500,000 |
| Gardiner, ME |
7/1983 |
1,150 |
6,500,000 |
| Pownal, VT |
10/1983 |
350 |
3,500,000 |
| Sebec, ME |
12/1984 |
880 |
3,164,000 |
| Collins, MA |
12/1984 |
1,500 |
5,640,000 |
| Bangor, ME
(abandoned) |
12/1987 |
24,000 |
96,000,000 |
| Greenville, ME |
12/1986 |
15,000 |
92,000,000 |
| Errol, NH |
12/1986 |
3,500 |
14,300,000 |
| Swanzey, NH
(abandoned) |
5/1988 |
17,500 |
119,600,000 |
| Stewartstown, NH (abandoned) |
8/1988 |
13,800 |
102,800,000 |
| Brassua, ME |
5/1990 |
3,400 |
14,800,000 |

Greenville
Steam Co. |